Capital Improvements Projects

146th Street SW Sewer Extension

Spring Street to 200 feet west of Woodbrook Road

The 146th Street SW Sewer Extension will install sanitary sewer facilities along 146th Street SW between Spring Street and 200 feet west of Woodbrook Road. Other improvements include new pavement, gravel path, and storm drainage.  The construction for this project will begin summer of 2011 and is expected to be completed by the end of March 2012.   Through the construction duration, 146th Street will be closed to through traffic allowing local access only.

Project Manager: Troy Pokswinski, P.E.

Tillicum / Woodbrook Sewer Connections

After completion of over $18 Million in improvements in the communities of Tillicum and Woodbrook to extend sewer and provide storm drainage improvements (see attached map), the sewer system will ready for hook-ups (Tillicum: October 2011; Woodbrook: February 2012).

Mandatory Sewer Connections

Per City of Lakewood Municipal Code, section 12A.15, all properties adjacent to the newly-constructed sewer main will be required to connect to the sewer.  A property owner choosing not to connect to the sewer within 90-days of “notice of availability” shall pay the City of Lakewood a monthly availability charge prior to making the connection.  The “availability” charge is equivalent to the monthly sewer service charge (including all applicable fees, taxes, and surcharges).  Property owners will have 5 years from “notice of availability” to connect to the sewer.

Sewer Connection Loan Programs

Limited funds are available to assist with connecting to the sewer.  Contact (253) 983-7795 for additional information.

Project Manager: Desiree Winkler, P.E.

Project Contact Information:
Phone: (253) 983-7795
Email: sewerproject@cityoflakewood.us

100th Street

Gravelly Lake Drive to 59th Avenue

This project provides curb, gutter, sidewalk, street lighting, and associated storm drainage to 100th Street between Gravelly Lake Drive and 59th Avenue.  In addition the traffic signal at Gravelly Lake Drive and 100th Street will be replaced and the entire project limits repaved.

Project construction is scheduled to begin January 2012 and continue through June 2012.  Utility relocation work will begin November 2011.  During roadway construction, 100th Street will be reduced to one travel lane each direction 24 hours a day / 7 days per week.  Additional night time closures will be required toward the end of construction schedule to facilitate paving.

Project Manager: Eric Swanstrom, P.E.

Bridgeport Way

75th Street W to North City Limits

This project completes curb, gutter, sidewalk, street lighting, and associated storm drainage to Bridgeport Way between 75th Street W and the North City limits.  If funding allows, the traffic signal at Bridgeport Way and 75th Street will be replaced and the road re-paved.

Utility relocation at the north end of the project limits will take place September 2011 through February 2012.  During this work, one side of the roadway will be reduced to one travel lane.

Project construction is scheduled to begin April 2012 and continue through October 2012.  Project construction will require reduction of the travel lanes to one lane each direction during day time hours.  Additional night time lane closures will be required toward the end of construction to facilitate paving.

Project Manager: Weston Ott, P.E.

150th Street / Murray Road Roundabout

The 150th Street / Murray Road intersection in Woodbrook will be replaced with a modern roundabout to improve traffic flow through this congested intersection.  The roundabout will be constructed on WSDOT-owned property adjacent to the current 3-leg intersection.

Construction is currently scheduled take place between March and August 2012. 

Project Manager: Troy Pokswinski, P.E.

e1163 Brochure

 

Lakewood Station Connection Project

bridge rendering

Lakewood Station Connection Pedestrian
Bridge Rendering (courtesy of Hewitt and KPFF)

This project provides a pedestrian overpass connecting the Lakewood Commuter Rail/Transit Station to Kendrick Street on the north side of the tracks.  In addition, roadway improvements will be completed on Kendrick Street from the proposed pedestrian overpass to 111th Street.

Project Limits

Project construction is scheduled for March 2012 through October 2012.

Project Manager: Jeff Gonzalez, P.E.

 

Traffic Signal System Upgrades - City Wide

The projection is currently implementing a new traffic signal control system starting on Steilacoom Boulevard, Gravelly Lake Drive, and Bridgeport Way.  The new system will enable City staff increase traffic flow throughout the City.

Project Engineer: John Howe & DKS Engineering

2012 Drywell Replacement Project

This project will replace approximately 115 obsolete stormwater drywells with two-stage infiltration systems.  This will improve the quality of the stormwater by removing many pollutants before it enters the groundwater.  The project area is generally all remaining drywells located west of Lake Steilacoom from 112th St. SW to north side of the Oakbrook neighborhood.

Construction is tentatively scheduled to take place between June and October 2012.

Project Manager: Troy Pokswinski, P.E.

Mountain View Outfall Water Quality Project

This project will retrofit an existing stormwater outfall that currently discharges untreated stormwater into a pond located just upstream of the headwaters of Flett Creek.  The project will install a water quality treatment structure into the existing stormwater conveyance system upstream of the existing outfall.  The treatment structure is designed to remove oil and sediment from the stormwater thus improving water quality before discharging to the pond and creek.  The project will be located along the stormwater conveyance system in the vicinity of Steilacoom Blvd. and Mountain View Cemetery.

Construction is tentatively scheduled to take place in the summer of 2012.

Project Manager: Greg Vigoren, P.E.

Outfall Water Quality Program

This project will retrofit several stormwater outfalls that currently discharge untreated stormwater into various creeks and lakes in Lakewood.  Depending on the location, the project will install water quality treatment structures upstream of outfalls; or remove outfalls; or reduce the amount of runoff reaching outfalls; or combinations of the above.  Various treatment structures and design options will be considered depending on the charactistics of each site.  The project location will be various stormwater outfalls located throughout the city.

Construction is tentatively scheduled to take place in the summer of 2012.

Project Manager: Greg Vigoren, P.E.

Clover Creek Fish Passage Project

This project is in the feasibility stage.  The City will be working with Pierce County and the neighboring property owners to consider removing or bypassing a small falls on Clover Creek located approximately 600 feet upstream from the mouth of the creek at Lake Steilacoom.  This would allow more fish to get upstream of the falls and continue further up into the watershed, thus opening up habitat to more fish.

This project is in the feasibility stage; construction has not been scheduled.

Project Manager: Greg Vigoren, P.E.