Below is a schedule of construction work related to work on South Tacoma, between State Route 512 and 96th Street in the City of Lakewood, for the upcoming week:

  • Tuesday, May 31: Contractor (Pape & Sons) will install water line on the west side of South Tacoma Way between Enterprise Rent-A-Car and 96th Street.
  • Wednesday, June 1: Contractor will install water line on the south side of 96th Street between South Tacoma Way and the project Limits at the Pierce Transit Training Building.
  • Thursday, June 2 to Friday, June 3: Contractor will install start installing storm on the west side of South Tacoma Way, starting at 96th Street and working their way south towards 100th Street.
  • Tuesday, May 31 to Friday, June 3: Subcontractor (DBE Electric) will install illumination, fiber, and spare conduit on the west side of South Tacoma Way, starting at Perkins Lane and moving north towards 96th Street. The contractor is not planning any night work for the upcoming week. The contractor/subcontractor will be closing a maximum of one lane at all times, and that will be the outside southbound lane (right lane) on South Tacoma Way between 96th & Perkins, as well as the outside eastbound lane (right lane) on 96th between the Pierce Transit Training Building & South Tacoma Way.